Setting 2027 Rates and Multipliers in Deltek Ajera: Make the System Match Your Profit Targets

QUICK ANSWER

To set 2027 rates in Deltek Ajera, start from the profit you want and work backward. Your break-even net multiplier is 1 plus your overhead rate. Your target multiplier is that figure divided by 1 minus your profit margin. Multiply each person’s direct labor cost by the target, raise it to cover the share of value you usually do not collect, and enter the result in an Ajera billing rate table dated from January 1, 2027, so past billing stays as it was.

Many firms set next year’s rates by adding a few percent to this year’s. That keeps rates moving, but it says nothing about profit. If overhead grew faster than rates, or a raise cycle lifted cost rates, a 4 percent increase can still leave the firm earning less per hour of direct labor than it did a year ago.

Firms come to us already running Deltek Ajera, and the question is rarely the software. It is whether the numbers inside it still match the firm’s plan. The rate table is where that plan becomes an invoice, so it is the right place to start 2027.

What net multiplier does my firm need in 2027?

Your break-even net multiplier is 1 plus your overhead rate, and your target is that figure divided by 1 minus the profit margin you want on net revenue. A firm with a 155 percent overhead rate that wants a 15 percent margin needs a net multiplier of 3.0, before any write-offs.

Two definitions make the math work. Net multiplier is gross billings minus subconsultant costs, divided by direct labor cost. Overhead rate is total indirect costs divided by direct labor cost. At a 155 percent overhead rate, every dollar of direct labor carries $1.55 of overhead, so $2.55 of net revenue only breaks even. Divide 2.55 by 0.85 and you reach 3.0, the multiplier that leaves 15 percent of net revenue as profit.

The formula assumes next year’s overhead rate looks like this year’s. If you are adding staff, space or software, budget those first and recalculate the rate. The same applies to cost rates. California’s minimum wage rises to $17.40 an hour on January 1, 2027, and the exempt salary floor rises with it, so any salary changes that follow should be in the cost rates before you build billing rates on top of them.

How do I turn the target multiplier into billing rates?

Multiply each person’s direct labor cost per hour by the target multiplier, then raise it to cover the share of value you do not collect. If the firm usually realizes 90 percent of the value at its rates, a 3.0 target needs a rate table near 3.33, so a $50 an hour cost rate bills at about $167.

Realization is the amount you actually bill divided by the value of the hours at your standard rates. Write-offs, courtesy discounts and hours that never reach an invoice all pull it down. Use your own 2026 figure rather than a rule of thumb, because it varies by firm, by client and by project type. The worked example below runs the whole chain with round illustrative numbers.

Step (illustrative figures)ResultHow it is calculated
Overhead rate155%Total indirect costs divided by direct labor cost, 2026 actual adjusted for known 2027 changes
Break-even net multiplier2.551 plus the overhead rate
Profit target15% of net revenueOwner decision
Target net multiplier3.002.55 divided by (1 minus 0.15)
Realization90%Amount billed divided by value at standard rates, 2026 actual
Rate table multiplier3.333.00 divided by 0.90
Billing rate for a $50 an hour cost rateAbout $167 an hour$50 times 3.33

Check the result against what your clients will pay. A rate the market will not accept is not a rate. Where the math lands above that line, the answer sits in overhead, utilization or realization, not in the rate table.

The target applies to the firm’s direct labor as a whole, not to each person equally. Some firms set a different multiplier by role, because a principal’s cost rate can price their hours above what a client will pay while junior staff carry more room. That works as long as the blended result, weighted by the hours each role expects to bill in 2027, still reaches the target. Run the blend before you enter anything in the system.

Where do rates and multipliers live in Deltek Ajera?

In billing rate tables. Ajera sets the billing rate from the table selected for each project, and a table can price labor by employee, employee type or activity, using a markup on cost, a standard rate, or a combination of the two. Expenses and consultant costs are priced by activity and vendor.

Each table can carry several date ranges. Add a range that starts January 1, 2027 and leave the end date open, and the new rates apply from that date without changing anything already billed. Deltek’s help notes that firms can create as many tables as they need for different client arrangements, which matters when some contracts fix rates for their full term. Check active contracts before you point an existing project at a new table.

Deltek’s help also says that when a table uses markups, Ajera multiplies the labor cost by the markup percentage to set the billing amount. Before you roll the table out, preview one employee’s billing rate on a test project and confirm it produces the dollar figure you intended. Getting setup, billing and reporting to agree with each other is most of the work in an Ajera rate change.

Why does the multiplier we bill differ from the one we achieve?

Because the rate table prices hours, and not every hour gets billed at its rate. Write-offs, time over budget on fixed-fee work, unbilled hours and slow collections all pull the achieved net multiplier below the one built into the table.

On fixed-fee projects the fee sets what you can bill, so the rate table does not change the invoice. The hours spent against that fee still decide the multiplier you achieve. That is why fee burn against percent complete, covered in our September article on forecasting in Ajera, matters as much as the rate itself. Compare the billed multiplier with the achieved one every month, by project, and the gap tells you where 2027’s margin is leaking.

What should be done before January 1?

Five steps, in order: settle the overhead budget and cost rates, set the profit target, build the new rate table with a January 1 date range, test it on one project, and tell clients before the first 2027 invoice. The first two are decisions for the owner; the last three are setup work in Ajera.

1. Settle the 2027 overhead budget and update cost rates for raises and the California wage change, because every billing rate is built on them.

2. Set the profit target as a percentage of net revenue and calculate the target net multiplier from your own overhead rate.

3. Build the new billing rate table, or add a date range to the existing one, starting January 1, 2027.

4. Preview one employee’s rate on a test project and check it against the dollar figure you calculated.

5. Tell clients about new rates before the first 2027 invoice, and leave contracts with fixed rates on the table they were signed under.

Frequently asked questions

The one that covers your overhead and delivers your profit target. Industry surveys publish averages, but they blend firms of different size, discipline and region. Your break-even is 1 plus your own overhead rate, so start there and compare your result with your own firm last year.

At least once a year, with a new date range starting January 1 so past billing stays unchanged. Update sooner if cost rates move materially, for example after a raise cycle or a wage change that lifts salaries.

Yes. Deltek’s help says firms can create as many billing rate tables as they need to reflect billing arrangements with clients on particular projects, and Ajera uses the table selected for each project.

The fee sets what you bill, so the table does not change the invoice. The hours you spend against that fee still decide the multiplier you achieve, so watch fee burn against percent complete.

Yes. Summit Business Advisors LLC, West Los Angeles, works as an Ajera consultant for architecture and engineering firms on setup, billing and reporting inside Deltek Ajera, including billing rate tables, alongside project accounting and controller-level support.

NEXT STEP

Book an Ajera review. Summit Business Advisors LLC, West Los Angeles, works with architecture and engineering firms that already run Deltek Ajera and want more from it. An Ajera review looks at your rate tables, project setup and the reports you use to make decisions, and tells you what to change before January 1.

summitadvisorsla.com/contact-us/